This post contains pictures from the week ending October 8, 2017.

Backfill was completed.  Infiltration trenches laid out and covered with BMP materials.  Gravel has been placed in the footprint of the foundation.  Visqueen plastic will be placed near the end of the project to complete the Vapor Barrier process.

Sub-Floor framing will begin on Monday of next week with underfloor MEP’s to follow.

Have a wonderful weekend.