The framers raised the exterior walls of the work rooms and guest bedroom. They also installed and sheeted the upper floor. The plumbers installed the floor tubing at the master wing, and we followed that with the concrete crew pouring the master wing concrete floor. Pavilion steel was delivered last Thursday, and installation began. On Friday, the control joints were saw cut into the master wing floor.